SECI issues tender for 2 MW solar with 1 MW battery energy storage system

Solar Energy Corporation of India has issued a tender for the development of 2 MW (AC) of solar projects with 1 MW of battery energy storage system (BESS) at Kaza in Spiti Valley of Himachal Pradesh.

The successful bidder will be expected to complete the entire scope of work within 18 months from the date of issuance of the Notice of Availability (NoA).

The scope of work includes the design, engineering, supply, construction, installation, testing, and commissioning of the projects. Apart from these, the successful bidder will also be responsible for 5 years of operations and maintenance (O&M) services. This would include the supply and storage of all mandatory spare parts, consumables, repairs and replacements of any defective equipment during the O&M period.

Pre-bid meeting will take place on August 13, 2018 and last date for bid submission is August 31, 2018. Consortiums or joint ventures are allowed to bid for the projects.

Image Credit : mercomindia.com

Related Stories:

Get Latest Updates Via Email