MMRDA starts casting work for first segment of package-3 of MTHL

Casting work for the first segment of the package-3 of the ambitious Mumbai Trans Harbour Link (MTHL) bridge, which will connect Sewri with Nhava Sheva, has commenced.

Sanjay Khandare, Additional Metropolitan Commissioner said, MTHL is a very significant project as far as connectivity between Mumbai and Navi Mumbai is concerned, the very reason why the beginning of the casting of its first segment in package-3 of the entire project assumes so much importance.”

The package-3 consists of the construction of 2.5-km viaduct and 1.5-km at grade work from Gavan village to Chirle Village connecting NH-4B. The Mumbai Trans Harbour Link project which costs a whopping Rs 17,843 crore has been divided into three packages.

The work in package-1 includes running from Sewri up to 10.38-km (10.38 km), Package-2 includes running from step 10.38-km up to step 18.187-km (7.807 km) and in package-3 work includes running from step 18.187 up to Chirle village (3.613 km)

Image Credit : hindustantimes.com

Research Desk

Next Post

Icono India Infotech to manufacture LED TV from Raigad

Tue Sep 17 , 2019
Icono India Infotech Pvt Ltd has proposed to manufacture LED TVs from Raigad (Kulaba), Maharashtra. In connection with this, it has filed an Industrial Entrepreneurs’ Memorandum with the Commerce Ministry’s Department of Industrial Policy and Promotion (DIPP). Other companies which have filed IEMs are KPIT Technologies Ltd for architectural and […]
Shakun Polymers

Categories

Blog Stats