MMRDA starts casting work for first segment of package-3 of MTHL

Casting work for the first segment of the package-3 of the ambitious Mumbai Trans Harbour Link (MTHL) bridge, which will connect Sewri with Nhava Sheva, has commenced.

Sanjay Khandare, Additional Metropolitan Commissioner said, MTHL is a very significant project as far as connectivity between Mumbai and Navi Mumbai is concerned, the very reason why the beginning of the casting of its first segment in package-3 of the entire project assumes so much importance.”

The package-3 consists of the construction of 2.5-km viaduct and 1.5-km at grade work from Gavan village to Chirle Village connecting NH-4B. The Mumbai Trans Harbour Link project which costs a whopping Rs 17,843 crore has been divided into three packages.

The work in package-1 includes running from Sewri up to 10.38-km (10.38 km), Package-2 includes running from step 10.38-km up to step 18.187-km (7.807 km) and in package-3 work includes running from step 18.187 up to Chirle village (3.613 km)

Image Credit : hindustantimes.com

Tags:
Download Now – Special Research Report

A 110 page special research report that highlights around 580 key investments happened in the year 2018-19.

Daily Newsletter

Enter your email address:

Delivered by FeedBurner

Archives