60% of 4-laning of Gagalheri-Saharanpur-Yamunanagar completed

Welspun Enterprises has given an update that ‘physical progress of about 60 per cent has been completed’ for the four-laning of Gagalheri -Saharanpur-Yamunanagar section of NH-73 in Uttar Pradesh / Haryana.
The bid project cost is Rs 11.84 billion.

As far as the six-laning of Delhi -Meerut Expressway and four-laning either side from 0th km to existing km 8.4 of NH-24 in Delhi is concerned, the status is as follows: “Received the first annuity in January 2019 within the stipulated time of 15 days from the completion of 6 months from COD. The COD was achieved 11 months ahead of the scheduled date.” The completion cost is Rs 8.87 billion.

Physical progress of about 60% has been completed by Q4FY19 for 4-Laning of Chutmalpur-Ganeshpur section of NH-72A & Roorkee-Chutmalpur-Gagalheri section of NH-73 in UP & Uttarakhand. The bid project cost is Rs 9.42 billion.

Image Credit : proptiger.com

Download Now – Special Research Report

A 110 page special research report that highlights around 580 key investments happened in the year 2018-19.

Daily Newsletter

Enter your email address:

Delivered by FeedBurner

Archives