50% work completed on 4-lane Dera Baba Nanak-Kartarpur corridor highway

Fifty per cent of the construction work on a four-lane highway connecting Dera Baba Nanak from Gurdaspur-Amritsar highway to International border has been completed.

The 4.19 km long highway is being built at a cost of Rs 120 crore. The Karatarpur Sahib Corridor project was approved by the Government of India on 22.11.2018 and the foundation stone was laid by Vice President M Venkaiah Naidu on 26.11.2018.

According to a report in 5dariyanews.com, the land acquisition process for the project was initiated on 14.01.2019 and concluded on 21.05.2019.

“So far, 50 per cent of the project work has been completed and the Highway would be completed by September 30, 2019. The substructure construction work of the bridge i.e., piling, pile caps has been completed on the Indian side. Piers and Piers caps casting work is under progress along with girder casting work,” it added.

Image Credit : static-news.moneycontrol.com

Download Now – Special Research Report

A 110 page special research report that highlights around 580 key investments happened in the year 2018-19.

Daily Newsletter

Enter your email address:

Delivered by FeedBurner

Archives